The EU's network codes and guidelines for electricity are crucial for maintaining security of energy supply, increasing competitiveness and ensuring that all consumers can buy energy at affordable prices.
An interconnected electricity market
Europe’s cross-border electricity networks are operated according to rules that help govern the work of operators and determine how access to electricity is given to users across the EU. In the past, these grid operation and trading rules were drawn up nationally. As electricity is increasingly interconnected between countries, the EU-wide rules effectively manage these electricity flows in the internal energy market.
These rules, known as network codes or guidelines, are legally binding Commission implementing regulations. They govern all cross-border electricity market transactions and system operations alongside the Electricity Regulation (EU/2019/943) which establishes rules and principles to ensure the functioning of the internal market for electricity.
Development of network codes and guidelines
Every 3 years, the Commission draws up a 'priority list' of areas to be included in the development of network codes for electricity, with input from a public consultation.
The Commission, with further input from the Agency for the Cooperation of Energy Regulators (ACER), the European Network of Transmission System Operators for Electricity (ENTSO-E), the EU DSO entity and the other relevant stakeholders, adopts proposals for network codes. The proposals for network codes are checked by an electricity cross-border committee of specialists from national energy ministries.
Sometimes the new rules are adopted as 'guidelines' rather than 'network codes'. These are adopted under a different provision of the Electricity Regulation (EU/2019/943) but they have the same status – they are both legally binding regulations.
Market and trading network codes and guidelines
Capacity allocation and congestion management
The Regulation establishing a guideline on capacity allocation and congestion management (CACM) (EU/2015/1222) entered into force on 15 August 2015. The provisions of CACM govern the establishment of cross-border EU electricity markets in the day-ahead and intraday timeframes, as well as methods for the calculation of interconnection capacity.
Forward capacity allocation
The Regulation establishing a guideline on forward capacity allocation (FCA) (EU/2016/1719) entered into force on 17 October 2016. The provisions of FCA establish a framework for the calculation and allocation of interconnection capacity, and for cross-border trading, in forward markets (timeframes longer than day-ahead).
Balancing
The Regulation establishing a guideline on electricity balancing (EB) (EU/2017/2195) entered into force on 18 December 2017. The balancing guideline sets down rules on the operation of balancing markets - those markets that transmission system operators (TSOs) use to procure energy and capacity to keep the system in balance in real time. The objectives of the guideline include increasing the opportunities for cross-border trading and the efficiency of balancing markets.
Demand response
The Commission is developing a Network Code on Demand Response to ensure that demand response resources can fully participate in all wholesale electricity markets and set out clear rules so that local services (such as congestion management and voltage control) are procured transparently and efficiently by system operators.
Local Flexibility Markets (LFMs), which are developing at different rates across Europe, are central to unlocking the required flexibility. In March 2026, the Commission published a Study on specification and design criteria for LFMs to help EU countries establish LFMs that are effective, adapted to local contexts, and well-integrated into the wider electricity system.
Emergency and restoration
The Regulation establishing a network code on emergency and restoration (EU/2017/2196) entered into force on 18 December 2017. The emergency and restoration network code sets down rules relating to the management of the electricity transmission system in the emergency, blackout and restoration states. The main objective of the relevant rules is to bring the system back to the normal state.
Demand connection
The Regulation establishing a network code on demand connection (DCC) (EU/2016/1388) entered into force on 7 September 2016. The provisions of DCC set out detailed rules relating to the connection of, principally, new demand facilities to national electricity networks.
Requirements for generators
The Regulation establishing a network code on requirement for grid connection of generators (EU/2016/631) entered into force on 17 May 2016. The provisions of the regulation set out detailed rules relating to the connection of, principally, new power generating installations to national electricity networks.
High-voltage direct current
The Regulation establishing a network code on requirements for grid connection of high-voltage direct current system and direct current-connected power park modules (HVDC) (EU/2016/1447) entered into force on 28 September 2016. The provisions of HVDC set out detailed rules relating to the connection of, principally, new high-voltage direct current systems to national electricity networks.
System operation
The Regulation establishing a guideline on electricity transmission system operation (SO) (EU/2017/1485) entered into force on 14 September 2017. The provisions of SO establish a framework for the maintenance of the secure operation of the interconnected transmission system in real time.
The Electricity Regulatory Forum (Florence Forum)
The Electricity Regulatory Forum, also referred to as the Florence Forum, was set up to discuss the creation of the internal electricity market.
Participants include national regulatory authorities, EU countries’ governments, the Commission, transmission system operators, electricity traders, consumers, network users, and power exchanges.
Since 1998, the forum has met once per year in Italy.

The meeting presentations and reports from all Florence forums are listed in chronological order in a dedicated document management tool (CIRCABC), which is open to the public. The most recent meetings are listed below
- 41st meeting of European Electricity Regulatory Forum (28-29 May 2026)
- 40th meeting of the European Electricity Regulatory Forum | Event page (12-13 June 2025)
- 39th meeting of the European Electricity Regulatory Forum (27-28 May 2024)
Related links
- Security of electricity supply
- Commission Decision on the establishment of the annual priority lists for the development of network codes and guidelines for 2018 (2018/496/EU); 2017 (2017/89/EU); 2016 (2015/1960)
- Electricity Regulation (EU/2019/943)
- Commission Regulation (EU) No 543/2013 on submission and publication of data in electricity markets and amending Annex I to Regulation (EC) No 714/2009 of the European Parliament and of the Council
- Regulation on laying down guidelines relating to the inter-transmission system operator compensation mechanism and a common regulatory approach to transmission charging (838/2010/EU)
- Study: Specification and design criteria for Local Flexibility Markets (March 2026)
- Study: Implementation of the network code on requirements for grid connection of generators (February 2021)