Global warming potential of buildings

The Energy Performance of Buildings Directive, revised in 2024, takes first steps towards the consideration of buildings’ life-cycle global warming potential. 

What is life-cycle global warming potential?

What emissions does it cover? 

The life-cycle global warming potential covers both 

  • operational emissions – due to the energy consumed for the building’s operation, notably heating and cooling
  • embodied emissions – associated with the production, transport, and life-cycle of materials used for construction and maintenance, demolition and waste management 

New construction in the EU accounts for 18% of the total whole life-cycle emissions from the building stock, even though it only represents 1% of the total floor area. Construction and demolition waste represents 40% of the waste generated in the EU.

What buildings fall under these rules? 

The revised directive requires that the life-cycle global warming potential is calculated and disclosed in the energy performance certificate for all new buildings with a floor area larger than 1 000 m² from 2028. This requirement will extend to all new buildings as of 2030.

  • An energy performance certificate (EPC) is a label rating the energy performance of buildings.

The calculation – carried out by building designers or other building professionals - will be based on national methodologies, which must respect the Union framework rules. 

By 2027, all EU countries will develop a roadmap for the introduction of limit values for the life-cycle global warming potential of all new buildings from 2030.

Promoting sustainable construction

Timeline for the life-cycle global warming potential

  1. January 2030

    All new buildings → life-cycle GWP is calculated and disclosed in the energy performance certificate.

  2. January 2028

    New buildings with over 1 000 m2 of useful floor area → life-cycle GWP is calculated and disclosed in the energy performance certificate.

  3. January 2027

    EU countries publish and notify to the Commission a roadmap on the introduction of limit values and targets.

  4. May 2026

    Entry into force of delegated act setting out a Union framework for the national calculation of life-cycle GWP.

  5. May 2024

    Publication of the revised Energy Performance of Buildings Directive in the Official Journal of the EU and entry into force 20 days later.